FLL North Runway Rehabilitation

  • LOCATION: Fort Lauderdale-Hollywood Airport

  • OWNER: Broward County Aviation Department -and- General Asphalt

  • CONTRACT: $6.6 Million Dollars

The project comprises of the reconstruction of the North Runway 10L-28R with the replacement of the keel section, reconstruction of taxiway connectors, reconstruction of the existing EMAS Beds, relocation of two Taxiways (D & T2), and miscellaneous drainage improvements. Project improvements included over 80,000 CY of excavation, 160,000 SY of clearing and grubbing, 221,000 SY of compacted subgrade, 81,000 SY of limerock base, 1,500 LF of drainage, 14,000 LF of pipe cleaning and inspection, as well as the installation of 8 aircraft rated drainage structures and a cast in place trench drain.